Executive Brief
The European Union's PCI/PMI process is a mechanism for choosing which cross-border energy bottlenecks deserve political priority, accelerated permitting, coordinated regulation and potential access to EU co-financing. In electricity, the process has moved from completing missing national interconnections to building a system capable of integrating large volumes of renewable power, offshore generation, storage and digitally managed flexibility.
The strategic question is no longer only where to build another line. It is how to create a resilient European electricity system able to move power across borders, reduce curtailment, withstand physical and cyber risks, connect offshore generation and limit the cost of electrification. PCI or PMI status signals that the EU considers a project relevant to this continental system rather than merely to one national network.
The third Union-list exercise opened in 2026 against a more demanding background: rapid renewable deployment, growing connection queues, rising electricity demand from industry and data centres, security concerns around critical infrastructure, supply-chain constraints and public resistance to new lines. Competition for status is therefore also competition for regulatory attention, political coordination and scarce public support.
Status does not amount to a construction authorisation or a grant award. It places a project in a privileged regulatory pipeline. Financing remains project-specific and may combine regulated tariffs, promoter equity and debt, national measures, European Investment Bank financing and grants from the Connecting Europe Facility (CEF Energy). The distinction between strategic selection and financial award is central to interpreting the figures in this briefing.
1. What this eBriefing covers
- The political and strategic rationale behind EU cross-border electricity infrastructure policy.
- The meaning of PCI and PMI status and the legal consequences of inclusion in the Union list.
- The first and second PCI/PMI lists under the revised TEN-E Regulation and the third-list process launched in 2026.
- CEF Energy funding rounds, with a clear separation between EU grants and the wider financing structure of a project.
- The institutions, Regional Groups, regulators, system operators and decision-making bodies involved.
- The position of unsuccessful applicants, institutional scrutiny and possible legal remedies.
- Practical implications for TSOs, DSOs, technology suppliers, investors, industrial users, public authorities and advisers.
2. The policy and strategic logic
2.1 From national networks to a European system
Electricity systems were historically planned mainly around national generation fleets and demand centres. Decarbonisation changes the geography and timing of power flows. Offshore wind, solar generation, hydro resources and storage are unevenly distributed; their value depends on the ability to transmit electricity across regions and borders. Interconnectors can reduce isolation, improve competition, provide balancing options and lower the volume of renewable generation that must be curtailed.
2.2 Security and geopolitical resilience
The synchronisation of Estonia, Latvia and Lithuania with the Continental European Network on 9 February 2025 illustrates the geopolitical dimension. It ended the Baltic systems' reliance on the Russian- and Belarusian-controlled synchronous area. The second Union list and subsequent CEF awards also place greater emphasis on resilience and protection of critical electricity infrastructure.
2.3 Industrial and investment consequences
Grid availability increasingly affects industrial location, electrification projects, renewable deployment and data-intensive investment. Delayed interconnection can create regional price differences, connection queues and curtailment. For private operators, PCI/PMI status can improve visibility and coordination but does not remove construction, permitting, procurement, cost-recovery or demand risks.
3. What PCI and PMI status means
| Status | Scope | Core requirement | Practical effect |
|---|---|---|---|
| PCI — Project of Common Interest | Infrastructure linking or significantly affecting at least two EU Member States | Contribution to a TEN-E priority corridor or area; cross-border impact; sustainability and category-specific benefits | Accelerated permitting, regulatory coordination, visibility and possible eligibility for CEF Energy |
| PMI — Project of Mutual Interest | Eligible infrastructure linking the EU with one or more third countries | Mutual benefit; EU-level net socio-economic benefits; security and decarbonisation contribution; policy convergence in the partner country | Similar Union-list advantages, subject to PMI-specific eligibility and third-country conditions |
Only specified infrastructure categories are eligible. For PMIs, the permitted categories are narrower and include electricity transmission, offshore hybrid interconnectors, hydrogen transmission and CO2 networks, potentially linked to storage.
4. How the selection works
- System-needs identification and TYNDP entry. Electricity transmission and storage candidates must be included in the latest available ENTSO-E Ten-Year Network Development Plan. ENTSO-E applies its cost-benefit methodology and future-system scenarios.
- Application. Project promoters submit data through the Commission's open call, identifying the relevant corridor or thematic area and providing technical, economic, environmental and maturity evidence.
- Eligibility screening. The Commission and technical bodies verify scope, cross-border dimension, TYNDP status where required and completeness.
- Technical assessment. Candidate projects are assessed against Article 4 of TEN-E, including sustainability, market integration, security of supply, competition, renewable integration and cost-benefit indicators.
- Public consultation and stakeholder scrutiny. Candidate projects are published for consultation; stakeholders can comment on need, impacts and maturity.
- Regional Group evaluation and ranking. Regional Groups examine the evidence. Their Decision-Making Bodies — Member States and the Commission — adopt regional proposals.
- ACER opinion and consistency review. ACER contributes regulatory assessment and opinions during the process, particularly regarding consistent application of criteria and cross-border impacts.
- Delegated act. The Commission adopts the Union list as a delegated regulation.
- Parliamentary and Council scrutiny. Parliament and Council may object to the list as a whole within two months, extendable by two months; they cannot amend individual projects.
- Entry into force and implementation monitoring. Listed projects move into permitting, regulatory, financing and construction phases; unjustified delays can affect later list exercises.
5. Selection criteria for electricity projects
| Criterion | What applicants should demonstrate |
|---|---|
| Corridor relevance | The project is necessary for at least one TEN-E priority electricity or offshore corridor, or an eligible thematic area. |
| Cross-border impact | A significant impact in at least two Member States; for PMIs, demonstrable Union-level and partner-country benefits. |
| Sustainability | Material contribution to renewable integration, reduced curtailment, lower emissions or efficient system operation. |
| Market integration and competition | Additional transfer capability, reduced congestion, price convergence or increased supply options. |
| Security and resilience | Improved adequacy, diversification, operational security or resilience of critical infrastructure. |
| Socio-economic value | Benefits that outweigh costs under the applicable cost-benefit methodology and scenario assumptions. |
| Maturity and deliverability | Credible promoter structure, schedule, permitting plan, technical design and stakeholder engagement. |
| Consistency with network planning | Inclusion in the latest TYNDP where required and alignment with identified European system needs. |
6. Union lists: the selection tranches
| Selection tranche | Legal act / publication | Result | Electricity focus | Interpretation |
|---|---|---|---|---|
| Legacy PCI lists | 2013, 2015, 2017, 2019 and 2021 lists under the former TEN-E framework | Successive lists of electricity and gas PCIs | Interconnections, security of supply, market integration and completion of missing links | Created the permitting, regulatory and CEF pipeline used by many current flagship projects. |
| First PCI/PMI Union list | Delegated Regulation (EU) 2024/1041; published 8 April 2024 | 166 PCIs and PMIs | 85 electricity, offshore and smart-grid projects; many expected between 2027 and 2030 | First list under revised TEN-E; introduced PMIs and stronger climate-alignment requirements. |
| Second PCI/PMI Union list | Delegated Regulation (EU) 2026/764; published 9 April 2026 | 235 PCIs and PMIs | 113 electricity, offshore and smart-electricity-grid projects | Broader pipeline, greater resilience emphasis and more links with third countries. |
| Third PCI/PMI Union list | Applications in 2026; delegated act planned for November 2027 | Not yet selected | Electricity, offshore, storage and smart-grid applications assessed through 2027 | Expected to expose the next generation of system bottlenecks and investment priorities. |
7. What has already been selected: electricity portfolio highlights
The full legal lists contain project clusters and component investments. The table below highlights commercially and strategically relevant examples; it is not a substitute for the legal annex or the PCI/PMI Transparency Platform.
| Project / corridor | Countries | Type | Status at 22 Sep 2026 | Official information |
|---|---|---|---|---|
| Biscay Gulf | Spain-France | 2 GW HVDC submarine interconnector | Under construction; testing expected from mid-2027 and commissioning targeted for 2028 | INELFE project page |
| Celtic Interconnector | Ireland-France | 700 MW HVDC interconnector | Construction under way; land and converter-station works progressing | EirGrid project page |
| Baltic Synchronisation | Estonia-Latvia-Lithuania-Poland | Synchronous-area integration and grid reinforcement | Core synchronisation completed 9 February 2025; resilience investments continue | European Commission — BEMIP |
| Bornholm Energy Island | Denmark-Germany | Offshore energy hub and hybrid interconnector | Joint development and procurement advancing following 2026 political agreement | Official project website |
| Harmony Link | Lithuania-Poland | Electricity interconnection and Baltic integration | Included in the BEMIP electricity cluster; implementation configuration has evolved | PCI/PMI Transparency Platform |
| Triton Link | Belgium-Denmark | Offshore hybrid interconnector | Listed PCI; development and system-design phase | PCI/PMI Transparency Platform |
| Nautilus | Belgium-United Kingdom | Multi-purpose offshore interconnector (PMI) | Listed PMI; development and assessment phase | PCI/PMI Transparency Platform |
| LionLink | Netherlands-United Kingdom | Multi-purpose HVDC offshore interconnector (PMI) | Listed PMI; development phase | PCI/PMI Transparency Platform |
| Great Sea Interconnector | Greece-Cyprus-Israel | Submarine electricity interconnection | Listed cluster; complex financing and implementation risk requires continued monitoring | PCI/PMI Transparency Platform |
| AGUAYO II | Spain | Reversible pumped-storage hydro | CEF works grant awarded in 2026; construction support €180.03m | CINEA award information |
| CARMEN | Romania-Bulgaria | Cross-border smart grids | CEF works grant awarded in 2026; €103.69m | CINEA award information |
| Gabreta Smart Grids | Czechia-Germany | Smart distribution-grid cooperation | Listed PCI; implementation monitored through project and transparency sources | PCI/PMI Transparency Platform |
8. Funding: status is not a grant
PCI/PMI designation creates eligibility to apply for CEF Energy but does not guarantee support. CEF is EU-budget co-financing. The balance of project costs may be borne by regulated network tariffs, promoter resources, commercial or public debt, national budgets, other EU instruments or the EIB. The precise mix differs by project and can change over time.
| CEF tranche | Available / awarded | Outcome | Nature of finance |
|---|---|---|---|
| 2014-2020 programme | €4.7bn awarded across 149 actions | Studies and works for electricity, smart grids, gas and CO2 infrastructure | EU grants; not total project investment |
| 2021 call | €785m available | PCI studies and works under the 2021-2027 programme | EU CEF grants |
| 2022 call | €800m available | Clean-energy infrastructure proposals | EU CEF grants |
| 2023 call | €750m available | Projects on the fifth legacy PCI list | EU CEF grants |
| 2024 call — results Jan 2025 | €1.25bn awarded to 41 actions, above the initial €850m indicative budget | 5 works and 36 studies across electricity, hydrogen and CO2 | EU CEF grants; subsequent grant agreements managed by CINEA |
| 2025 call — results Jan 2026 | Approx. €650m awarded to 14 actions | 6 electricity/smart-grid actions and 8 hydrogen actions | EU CEF grants |
| 2026 call | €600m available; deadline 30 Sep 2026 | For eligible projects on the second PCI/PMI list | EU CEF co-financing; results pending |
8.1 Electricity awards from the 2025 CEF call
| Action | Country / type | EU grant (€m) |
|---|---|---|
| AGUAYO II reversible pumped-storage plant | Spain — works | 180.03 |
| Baltic critical synchronisation infrastructure protection | Poland, Estonia, Latvia, Lithuania — works | 112.58 |
| CARMEN smart grids | Romania-Bulgaria — works | 103.69 |
| Cierny Vah pumped-storage modernisation | Slovakia — works | 62.63 |
| GREGY Green Energy Interconnector final studies | Greece-Egypt — study | 9.56 |
| Westtirol-Zell/Ziller internal-line study | Austria — study | 1.02 |
These six electricity-related grants total approximately €469.51 million. The published amounts are EU grants, not necessarily the full investment costs of the underlying projects.
8.2 Cost allocation and national funding
For regulated electricity infrastructure, project promoters can submit an investment request to the relevant national regulatory authorities. Cross-border cost-allocation decisions determine how investment costs are distributed where costs and benefits fall in different countries. ACER monitors these decisions and may become involved where national regulators cannot agree. ACER's 2025 monitoring found that costs remained national in most cases and that access to CEF grants — not redistribution of costs — was often the principal reason for seeking a CBCA decision.
9. New deadlines and timetable
| Date / period | Milestone |
|---|---|
| 30 September 2026 | Deadline for hydrogen, electrolyser and CO2 candidate applications; also deadline for the separate 2026 CEF Energy call. |
| 13 November 2026 | Deadline for electricity transmission and storage candidate applications. |
| 4 December 2026 | Deadline for smart electricity grids, smart gas grids and Article 24 candidates. |
| December 2026-March 2027 | Public consultation on candidate projects. |
| October 2026-May 2027 | Regional Group and thematic-area meetings. |
| June-November 2027 | ACER opinion and Regional Group Decision-Making Body decisions. |
| November 2027 | Commission adoption/publication target for the delegated act. |
| December 2027-March 2028 | European Parliament and Council scrutiny. |
| April 2028 | Expected entry into force if no objection is raised. |
10. Who selects the projects
| Actor | Role |
|---|---|
| European Commission — DG Energy (DG ENER) | Runs the call and process, chairs Regional Groups, coordinates assessment and prepares/adopts the delegated act. |
| Regional Groups | Assess contribution to corridor priorities, compliance with criteria and maturity. Include Commission, Member States, TSOs, ENTSO-E/other relevant networks, promoters, national regulators and ACER; stakeholders may contribute. |
| Regional Group Decision-Making Bodies | Reserved to Member States and the Commission; adopt/rank proposed regional lists. |
| ENTSO-E | TYNDP system-needs work, project inclusion and electricity cost-benefit assessment under the applicable methodology. |
| ACER | Regulatory scrutiny and opinion; monitors cross-border cost allocation and may decide where national regulators disagree within its legal competence. |
| National regulatory authorities | Assess investment requests, regulatory treatment, incentives and cross-border cost allocation. |
| CINEA | Manages CEF Energy calls and grant agreements after the Commission's financing decisions; it does not decide the PCI/PMI Union list. |
| European Parliament and Council | Scrutinise the delegated act and may object to the list as a whole; they cannot amend individual entries. |
10.1 Expert participation and transparency
The process is not entrusted to a single independent jury. It combines technical assessment, network-planning evidence, regulatory input, stakeholder consultation and political decision-making in corridor-specific Regional Groups. The precise participants can vary by corridor and meeting. The legally decisive body is narrower than the broader group: only Member States and the Commission participate in the Regional Group Decision-Making Body.
For due diligence, operators should distinguish between: (i) experts and stakeholders contributing evidence; (ii) technical bodies producing scenarios and cost-benefit results; (iii) regulators providing opinions; and (iv) the Member State-Commission bodies making the regional selection decisions.
11. Final decision, objections and legal remedies
The Commission makes the final Union-level selection by adopting a delegated regulation containing the consolidated list. Parliament and Council may object to the act as a whole during the scrutiny period but cannot add, delete or rewrite individual projects.
Regulation (EU) 2022/869 does not establish a dedicated administrative appeal procedure through which an unsuccessful promoter can require reconsideration of its non-selection. Promoters should use consultation and procedural opportunities during the assessment to correct factual errors and document compliance.
General EU-law remedies may remain relevant. An action for annulment under Article 263 TFEU is theoretically available against reviewable EU acts, but a private applicant must satisfy strict standing requirements, including direct and individual concern where the act is not addressed to it. Judicial review of national permitting, regulatory, procurement or financing decisions follows the applicable national and EU rules. Complaints to the European Ombudsman may address maladministration but do not replace judicial proceedings.
12. What matters to public and private operators
| Operator | Commercial / policy relevance | Priority questions |
|---|---|---|
| TSOs and project promoters | Status can improve coordination, permitting pathway and CEF eligibility. | Is the project in TYNDP? Are CBA benefits robust across scenarios? Is cross-border governance documented? |
| DSOs and smart-grid consortia | Smart-grid status can support cross-border interoperability and renewable hosting capacity. | Are at least two Member States and relevant TSOs involved? Are data, cyber and interoperability arrangements mature? |
| Technology suppliers and EPC contractors | Selected pipelines signal future demand for HVDC, cables, substations, transformers, storage, digital controls and protection systems. | Which projects have moved from studies to works? Where are procurement and supply-chain bottlenecks? |
| Investors and lenders | Status reduces some regulatory risk but does not eliminate construction, revenue or political risk. | What is the regulated-asset treatment? Is a CBCA decision in place? What proportion is grant-funded? |
| Industrial energy users | Projects may affect regional capacity, congestion, prices and connection prospects. | When is commissioning realistic? Which zones benefit? Could delay change location or electrification decisions? |
| National and regional authorities | Projects can bring security and investment benefits but create planning, environmental and local-acceptance obligations. | Is the permitting authority resourced? Are cross-border timelines aligned? Is benefit-sharing credible? |
| Advisers, associations and research bodies | Consultations and Regional Group processes create opportunities to submit evidence. | Which assumptions can be tested? Are benefits and environmental impacts distributed fairly? |
13. Risk and opportunity dashboard
- Permitting risk -- PCI status accelerates procedures but does not waive environmental law or public participation.
- Cost inflation and supply-chain risk -- Cable, transformer, converter and specialist-vessel capacity can alter schedules and budgets.
- Cross-border governance risk -- Asymmetric national benefits can delay cost-sharing and political support.
- Demand and scenario risk -- A project justified under one electrification or renewable pathway may be less robust under another.
- Cyber and physical-security risk -- Offshore and cross-border assets are increasingly treated as critical infrastructure.
- Financing opportunity -- CEF grants can de-risk studies and works, while PCI/PMI visibility can assist EIB and private financing discussions.
- Procurement opportunity -- Moving from list status to funded works creates identifiable supplier markets.
- Data opportunity -- The Transparency Platform, TYNDP and CINEA grant data can support portfolio monitoring and early commercial intelligence.
14. EUGRID monitoring framework
| Indicator | Why monitor it | Primary source |
|---|---|---|
| List status and PCI/PMI number | Legal eligibility and continuity between biennial lists | EUR-Lex delegated regulations |
| TYNDP status and CBA indicators | System need, scenario robustness and maturity | ENTSO-E TYNDP project sheets |
| Permitting milestones | Schedule credibility | National competent authority / Transparency Platform |
| CBCA and incentive decisions | Cost recovery and cross-border allocation | National regulators and ACER |
| CEF application and award | EU grant support and transition from study to works | CINEA and Commission implementing decisions |
| Procurement notices | Commercial pipeline and delivery stage | TED, promoter and TSO procurement portals |
| Commissioning forecast | Timing of system and market impact | Promoter, TSO, TYNDP and Transparency Platform |
| Material changes or delisting | Execution risk and political reprioritisation | Successive Union lists and Regional Group material |
15. Primary sources and operational links
- Regulation (EU) 2022/869 (TEN-E)
- European Commission — PCI/PMI selection process and third-list timetable
- Second Union list — Delegated Regulation (EU) 2026/764
- First Union list — Delegated Regulation (EU) 2024/1041
- PCI/PMI Transparency Platform
- European Commission — Funding for PCIs and PMIs
- CINEA — 2024 call results (€1.25bn)
- CINEA — 2025 call results (€650m)
- ACER — Cross-border cost allocation
- ENTSO-E TYNDP 2024 project platform
- CINEA public project dashboard
- European Commission — BEMIP and Baltic synchronisation
Methodology and limitations
This first edition prioritises official EU legal acts, Commission and CINEA publications, ACER material, ENTSO-E sources and official project-promoter pages. Project status is time-sensitive and may differ between the legal Union list, promoter schedules and construction reality. Funding amounts reported as CEF support are EU grants unless stated otherwise; they must not be read as total project cost or as evidence that the balance is national public funding.
The legal Union list is definitive for PCI/PMI status. The Transparency Platform and TYNDP project sheets should be used for project-level monitoring, while promoter and national-authority sources should be checked before relying on commissioning dates, budgets or procurement status.
Disclaimer
The information contained in this eBriefing has been collected and processed by eEuropa from publicly available institutional, regulatory and market sources. It is provided for information purposes only and does not constitute legal, financial, investment or other professional advice.
While eEuropa makes reasonable efforts to ensure that the information is accurate and up to date, no guarantee is given as to its completeness or continued validity. Users should verify the applicable rules, decisions and conditions with the relevant institutions and competent authorities before taking business, legal or investment decisions.
eEuropa accepts no liability for any loss or damage arising from the use of, or reliance on, the information contained in this eBriefing.
Information available up to 23 September 2026.
© 2026 eEuropa. All rights reserved.